Choosing a machine

One machine runs plant-wide SCADA software with a few thousand tags and historical logging. What configuration and redundancy should we choose?

IPC247 engineering Answered on 2026-09-16
If the central SCADA machine fails, you lose visibility of the whole plant, so redundancy matters as much as the configuration. Reference configuration for a few thousand tags at a 1-second cycle with history: a current Core i5 or i7, 16–32 GB RAM, an industrial SSD for the operating system and a separate drive for historical data. Take exact figures from the SCADA vendor's recommendations, since each package uses resources differently. Redundancy at three levels: 1. Two drives in RAID 1, so the machine keeps running when one fails. 2. Dual power inputs, if the machine supports them. 3. Two machines in hot-standby (redundant server) mode, if the SCADA software offers it; this doubles the hardware but lets you replace a machine without losing monitoring. Network: at least two LAN ports, separating the control network from the office network. Back up the system image to another location regularly.

Read more

Related questions

I need an industrial PC that runs Linux, Android and Windows, with a 10 inch screen, USB, LAN, WiFi and a capacitive tou… We want to run AI inference right on the production line (edge AI): should we choose an NVIDIA Jetson-based machine or a… We need to mount computers on forklifts, AGVs and delivery trucks. How is that different from a machine inside an electr… Our project installs computers in railway carriages and requires EN 50155. What does that standard demand from the machi… We need a small machine to collect data from PLCs, power meters and sensors and push it to a server. What configuration …

Is your case different?

Leave your number — an engineer will call back with advice for your exact situation.

We only use this number to answer your request.